DMAIC Phase |
Activity |
Define |
Develop Project Charter
Write Problem Statement
Validate Voice of the Customer & Voice of the Business
Validate Financial Benefits
Develop SIPOC for process
Create Communication Plan
Select and Launch Team
Develop Project Schedule
Complete Define Gate |
Measure |
Value Stream Map for Deeper Understanding and Focus
Identify Key Input, Process and Output Metrics
Develop Operational Definitions
Develop Data Collection Plan
Validate Measurement System
Collect Baseline Data
Determine Process Capability
Complete Measure Gate |
|
|
|
|
|
|
|